Delhi: DDA Informs NGT It Will Complete O Zone Drone Survey in Two Months

New Delhi, April 22: The O zone is the entire floodplain along the 22-km stretch of the Yamuna in the city.
Encroachment Removal
DDA has reclaimed 7 acres after demolition drives on April 16 and 17 at:
-
Madanpur Khadar
-
Jhangola villages
-
Revenue Estate-Indraprastha
Drone Survey Details
-
Total area: 165 sq km
-
Phase 2 start date: February 5 (Green Zone)
-
Output per team: ~3.5 sq km per day
-
Teams deployed: 2
-
Remaining area to survey: 122 sq km
-
Estimated working days: 18 additional days
-
Post-processing time: ~1 additional month
Green and Red Zones
The Green and Red zones are part of the O zone.
Monitoring Measures
-
DDA has designated officers to ensure no further encroachment with continuous monitoring
-
MCD has also been asked to monitor
-
Police directed to ensure SHOs maintain vigilance against unauthorised constructions
-
Police to provide assistance to DDA whenever required
Background
The tribunal took suo motu cognisance of a TOI report in 2024 titled "161 illegal colonies on O zone making river water toxic" , which highlighted that colonies with 2.3 lakh households were unattached to the sewer network and contaminating the river.