Bangalore Development Body to Pay ₹56 Lakh Interest for Delay in Kempegowda Layout Amenities

Bengaluru, April 17: This comes as another major blow to BDA, whose NPKL project was flagged as lapsed by KRERA last year. The authority also ruled that BDA qualifies as a 'promoter' under RERA Act , making it liable for delays and deficiencies.
Case Details
-
Complainant: Mridula Krishnapur
-
Site location: 8th Block, Sector-B, NPKL, Kengeri hobli
-
Site cost: ₹96.9 lakh
-
Allotment date: October 11, 2018
-
Full payment by: February 5, 2019
-
Possession certificate: June 16, 2020 (site handed over without basic infrastructure)
Amenities Not Provided
-
Water
-
Sewerage
-
Electricity
-
Roads
-
Parks
-
Streetlights
KRERA's Observation
"To have a cosy house is everyone's dream. To fulfil that dream, one could take the risk of investing all lifetime savings... That being so, (if) the developer resorts to using the hard-earned money of investors in a reckless manner, it would not only shatter the dreams of investors, but also make them run from pillar to post."
Compensation Ordered
-
Interest amount: ₹56 lakh (for delay period June 10, 2020 – February 2, 2026)
-
Payment deadline: Within 60 days
-
Additional interest: From February 3, 2026, till completion of basic amenities
Authority Bench
-
Chairman: Rakesh Singh
-
Member: GR Reddy
-
Order date: April 8, 2026