Odisha: 244 Acres to Be Acquired for Jeypore Airport Upgrade

Koraput, April 24: The administration has identified around 244 acres of land across three villages for acquisition.
Current Status
-
Operational since: October 31, 2022 (under UDAN scheme)
-
Current operations: Two nine-seater flights daily (Bhubaneswar-Jeypore) + one daily (Jeypore-Visakhapatnam)
-
Runway length: 1,200 metres (existing)
Upgrade Details (Category 3C)
-
Land to be acquired: ~244 acres (including ~50 acres of government land)
-
New runway length: 2,700 metres
-
Aircraft capacity: 72-seater aircraft
-
Operations: 24/7 (without runway visual range limitations)
-
Feasibility report: Submitted by AAI in August 2024
Timeline
-
Detailed land schedule sent to government for notification
-
Work to begin once land is handed over
Official Statements
Sub-collector Jadumani Nayak: "The detailed land schedule has been sent to the government for notification. Once approved, the land acquisition process will begin."
Koraput Collector Manoj Satyawan Mahajan: "The airport upgrade will have a multiplier effect on the region, boosting economic activity, strengthening tourism and improving overall connectivity."